What is DRP, and what does a bank in Vietnam have to do to comply?

From a technical view, the DRP (disaster recovery plan) that SBV asks a bank for usually breaks down into 2 categories:

  • On-prem (requires a DC and a DR site): the test is to take the DC down and switch production traffic to the DR site.
  • Cloud (AWS, GCP, Azure): assume you deploy your system/app to 1 region with multiple AZs. You remove 1 availability zone (AZ) and see if the system keeps running.

SBV's circular (more on it below) doesn't set a minimum distance between the main and DR site. But it does ask you to assess disasters that could hit both at the same time, and a whole region going down is exactly that.

Which systems need DR?

Not all of them. And at a bank in Vietnam, you don't get to pick the rules. The State Bank (SBV) sets the tiers. You map each of your systems to one.

Circular 09/2020/TT-NHNN puts information systems into 5 levels. Roughly:

  • Level 1: internal systems with public information.
  • Level 3: systems serving customers 24/7, connections to third-party payment.
  • Level 4: systems holding data of 10 million customers or more.
  • Level 5: national systems connected internationally.

Online customer-facing systems get classified under Decree 85/2016/ND-CP, and the list has to be reviewed every year.

For me, level 3 is the line that matters. From level 3 up, the circular wants a real DR system and recovery within 4 hours. Below that, the rules are lighter. So the key step is to list your systems, put a level on each one, and let the level tell you how much DR it needs.

Plan the order

Each system on its own is usually fine. The hard part is the order. What comes up first, what depends on what, when the data starts flowing again. In my experience, ops or sysadmin teams plan in waves, a couple of months apart. Shared plumbing first: integration layer, core banking, API gateway. Then the apps sitting on top. If the plumbing isn't there, testing the apps tells you nothing.

Do a dry run, then a real one

A DRP that was never rehearsed is just a document. If you've never turned off the DC or removed the AZ, you don't know if it works. You hope it works. And a rehearsal that found problems is better than one that went perfectly. It means the test was real enough to hurt.

In Vietnam this isn't only my opinion. The circular is specific, and you need evidence for each of these:

  • Check the standby system at least every six months. To me, this is your dry run.
  • Actually switch production to it and run there for at least one working day. Every year for level 4 and up, every two years for level 3 and below. This is the real run.
  • Send the drill plan to SBV at least five working days before you run it.

That's the basics of DRP and how a regulator like SBV governs it. Hope this helps.